Home > Resources > Project Management for Construction
Folder Project Management
 
 
 
Project Management
 

01) The Owners' Perspective

Page 02 of 02 Chapter 01

02) Organizing For Project Management

Page 02 of 02 Chapter 02

03) The Design And Construction Process

Page 02 of 03 Chapter 03
Page 03 of 03 Chapter 03

04) Labor, Material, And Equipment Utilization

Page 02 of 03 Chapter 04
Page 03 of 03 Chapter 04

05) Cost Estimation

Page 02 of 03 Chapter 05
Page 03 of 03 Chapter 05

06) Economic Evaluation of Facility Investments

Page 02 of 03 Chapter 06
Page 03 of 03 Chapter 06

07) Financing of Constructed Facilities

Page 02 of 03 Chapter 07
Page 03 of 03 Chapter 07

08) Construction Pricing and Contracting

Page 02 of 03 Chapter 08
Page 03 of 03 Chapter 08

09) Construction Planning

Page 02 of 03 Chapter 09
Page 03 of 03 Chapter 09

10) Fundamental Scheduling Procedures

Page 02 of 03 Chapter 10
Page 03 of 03 Chapter 10

11) Advanced Scheduling Techniques

Page 02 of 03 Chapter 11
Page 03 of 03 Chapter 11

12) Cost Control, Monitoring, and Accounting

Page 02 of 03 Chapter 12
Page 03 of 03 Chapter 12

13) Quality Control and Safety During Construction

Page 02 of 03 Chapter 13
Page 03 of 03 Chapter 13

14) Organization and Use of Project Information

Page 02 of 03 Chapter 14
Page 03 of 03 Chapter 14

 
Folder 12. Cost Control, Monitoring and Accounting-02

12.4 Financial Accounting Systems and Cost Accounts

The cost accounts described in the previous sections provide only one of the various components in a financial accounting system. Before further discussing the use of cost accounts in project control, the relationship of project and financial accounting deserves mention. Accounting information is generally used for three distinct purposes:

  • Internal reporting to project managers for day-to-day planning, monitoring and control.
  • Internal reporting to managers for aiding strategic planning.
  • External reporting to owners, government, regulators and other outside parties.
  • External reports are constrained to particular forms and procedures by contractual reporting requirements or by generally accepted accounting practices. Preparation of such external reports is referred to as financial accounting. In contrast, cost or managerial accounting is intended to aid internal managers in their responsibilities of planning, monitoring and control.

    Project costs are always included in the system of financial accounts associated with an organization. At the heart of this system, all expense transactions are recorded in a general ledger. The general ledger of accounts forms the basis for management reports on particular projects as well as the financial accounts for an entire organization. Other components of a financial accounting system include:

  • The accounts payable journal is intended to provide records of bills received from vendors, material suppliers, subcontractors and other outside parties. Invoices of charges are recorded in this system as are checks issued in payment. Charges to individual cost accounts are relayed or posted to the General Ledger.
  • Accounts receivable journals provide the opposite function to that of accounts payable. In this journal, billings to clients are recorded as well as receipts. Revenues received are relayed to the general ledger.
  • Job cost ledgers summarize the charges associated with particular projects, arranged in the various cost accounts used for the project budget.
  • Inventory records are maintained to identify the amount of materials available at any time.
  • In traditional bookkeeping systems, day to day transactions are first recorded in journals. With double-entry bookkeeping, each transaction is recorded as both a debit and a credit to particular accounts in the ledger. For example, payment of a supplier's bill represents a debit or increase to a project cost account and a credit or reduction to the company's cash account. Periodically, the transaction information is summarized and transferred to ledger accounts. This process is called posting, and may be done instantaneously or daily in computerized systems.

    In reviewing accounting information, the concepts of flows and stocks should be kept in mind. Daily transactions typically reflect flows of dollar amounts entering or leaving the organization. Similarly, use or receipt of particular materials represent flows from or to inventory. An account balance represents the stock or cumulative amount of funds resulting from these daily flows. Information on both flows and stocks are needed to give an accurate view of an organization's state. In addition, forecasts of future changes are needed for effective management.

    Information from the general ledger is assembled for the organization's financial reports, including balance sheets and income statements for each period. These reports are the basic products of the financial accounting process and are often used to assess the performance of an organization. Table12-5 shows a typical income statement for a small construction firm, indicating a net profit of $ 330,000 after taxes. This statement summarizes the flows of transactions within a year. Table 12-6 shows the comparable balance sheet, indicated a net increase in retained earnings equal to the net profit. The balance sheet reflects the effects of income flows during the year on the overall worth of the organization.

    TABLE 12-5  Illustration of an Accounting Statement of Income

    TABLE 12-5  Illustration of an Accounting Statement of Income

    TABLE 12-6  Illustration of an Accounting Balance Sheet

    TABLE 12-6  Illustration of an Accounting Balance Sheet

    In the context of private construction firms, particular problems arise in the treatment of uncompleted contracts in financial reports. Under the "completed-contract" method, income is only reported for completed projects. Work on projects underway is only reported on the balance sheet, representing an asset if contract billings exceed costs or a liability if costs exceed billings. When a project is completed, the total net profit (or loss) is reported in the final period as income. Under the "percentage-of-completion" method, actual costs are reported on the income statement plus a proportion of all project revenues (or billings) equal to the proportion of work completed during the period. The proportion of work completed is computed as the ratio of costs incurred to date and the total estimated cost of the project. Thus, if twenty percent of a project was completed in a particular period at a direct cost of $180,000 and on a project with expected revenues of $1,000,000, then the contract revenues earned would be calculated as $1,000,000(0.2) = $200,000. This figure represents a profit and contribution to overhead of $200,000 - $180,000 = $20,000 for the period. Note that billings and actual receipts might be in excess or less than the calculated revenues of $200,000. On the balance sheet of an organization using the percentage-of-completion method, an asset is usually reported to reflect billings and the estimated or calculated earnings in excess of actual billings.

    As another example of the difference in the "percentage-of-completion" and the "completed-contract" methods, consider a three year project to construct a plant with the following cash flow for a contractor:

    Year
    Contract Expenses
    Payments Received
    1
    2
    3
    Total
    $700,000
    180,000
          320,000
    $1,200,000
    $900,000
    250,000
    150,000
    $1,300,000

    The supervising architect determines that 60% of the facility is complete in year 1 and 75% in year 2. Under the "percentage-of-completion" method, the net income in year 1 is $780,000 (60% of $1,300,000) less the $700,000 in expenses or $80,000. Under the "completed-contract" method, the entire profit of $100,000 would be reported in year 3.

    The "percentage-of-completion" method of reporting period earnings has the advantage of representing the actual estimated earnings in each period. As a result, the income stream and resulting profits are less susceptible to precipitate swings on the completion of a project as can occur with the "completed contract method" of calculating income. However, the "percentage-of-completion" has the disadvantage of relying upon estimates which can be manipulated to obscure the actual position of a company or which are difficult to reproduce by outside observers. There are also subtleties such as the deferral of all calculated income from a project until a minimum threshold of the project is completed. As a result, interpretation of the income statement and balance sheet of a private organization is not always straightforward. Finally, there are tax disadvantages from using the "percentage-of-completion" method since corporate taxes on expected profits may become due during the project rather than being deferred until the project completion. As an example of tax implications of the two reporting methods, a study of forty-seven construction firms conducted by the General Accounting Office found that $280 million in taxes were deferred from 1980 to 1984 through use of the "completed-contract" method.

    It should be apparent that the "percentage-of-completion" accounting provides only a rough estimate of the actual profit or status of a project. Also, the "completed contract" method of accounting is entirely retrospective and provides no guidance for management. This is only one example of the types of allocations that are introduced to correspond to generally accepted accounting practices, yet may not further the cause of good project management. Another common example is the use of equipment depreciation schedules to allocate equipment purchase costs. Allocations of costs or revenues to particular periods within a project may cause severe changes in particular indicators, but have no real meaning for good management or profit over the entire course of a project. As Johnson and Kaplan argue:

    Today's management accounting information, driven by the procedures and cycle of the organization's financial reporting system, is too late, too aggregated and too distorted to be relevant for managers' planning and control decisions....

    Management accounting reports are of little help to operating managers as they attempt to reduce costs and improve productivity. Frequently, the reports decrease productivity because they require operating managers to spend time attempting to understand and explain reported variances that have little to do with the economic and technological reality of their operations...

    The managagement accounting system also fails to provide accurate product costs. Cost are distributed to products by simplistic and arbitrary measures, usually direct labor based, that do not represent the demands made by each product on the firm's resources.

    As a result, complementary procedures to those used in traditional financial accounting are required to accomplish effective project control, as described in the preceding and following sections. While financial statements provide consistent and essential information on the condition of an entire organization, they need considerable interpretation and supplementation to be useful for project management.

    Example 12-5: Calculating net profit

    As an example of the calculation of net profit, suppose that a company began six jobs in a year, completing three jobs and having three jobs still underway at the end of the year. Details of the six jobs are shown in Table 12-7. What would be the company's net profit under, first, the "percentage-of-completion" and, second, the "completed contract method" accounting conventions?

    TABLE 12-7  Example of Financial Records of Projects

    TABLE 12-7  Example of Financial Records of Projects

    As shown in Table 12-7, a net profit of $1,054,000 was earned on the three completed jobs. Under the "completed contract" method, this total would be total profit. Under the percentage-of completion method, the year's expected profit on the projects underway would be added to this amount. For job 4, the expected profits are calculated as follows:

    Current contract price = Original contract price + Contract Changes
    = 4,200 + 400 + 4,600
    Credit or debit to date = Total costs to date - Payments received or due to date
    = 3,600 - 3,520 = - 80
    Contract value of uncompleted work = Current contract price - Payments received or due
    = 4,600 - 3,520 = 1,080
    Credit or debit to come = Contract value of uncompleted work - Estimated Cost to Complete
    = 1,080 - 500 = 580
    Estimated final gross profit = Credit or debit to date + Credit or debit to come
    = - 80. + 580. = 500
    Estimated total project costs = Contract price - Gross profit
    = 4,600 - 500 = 4,100
    Estimated Profit to date = Estimated final gross profit x Proportion of work complete
    = 500. (3600/4100)) = 439

    Similar calculations for the other jobs underway indicate estimated profits to date of $166,000 for Job 5 and -$32,000 for Job 6. As a result, the net profit using the "percentage-of-completion" method would be $1,627,000 for the year. Note that this figure would be altered in the event of multi-year projects in which net profits on projects completed or underway in this year were claimed in earlier periods.

    12.5 Control of Project Cash Flows

    Section 12.3 described the development of information for the control of project costs with respect to the various functional activities appearing in the project budget. Project managers also are involved with assessment of the overall status of the project, including the status of activities, financing, payments and receipts. These various items comprise the project and financing cash flows described in earlier chapters. These components include costs incurred (as described above), billings and receipts for billings to owners (for contractors), payable amounts to suppliers and contractors, financing plan cash flows (for bonds or other financial instruments), etc.

    As an example of cash flow control, consider the report shown in Table 12-8. In this case, costs are not divided into functional categories as in Table 12-4, such as labor, material, or equipment. Table 12-8 represents a summary of the project status as viewed from different components of the accounting system. Thus, the aggregation of different kinds of cost exposure or cost commitment shown in Table 12-0 has not been performed. The elements in Table 12-8 include:

  • Costs
    This is a summary of charges as reflected by the job cost accounts, including expenditures and estimated costs. This row provides an aggregate summary of the detailed activity cost information described in the previous section. For this example, the total costs as of July 2 (7/02) were $ 8,754,516, and the original cost estimate was $65,863,092, so the approximate percentage complete was 8,754,516/65,863,092 or 13.292%. However, the project manager now projects a cost of $66,545,263 for the project, representing an increase of $682,171 over the original estimate. This new estimate would reflect the actual percentage of work completed as well as other effects such as changes in unit prices for labor or materials. Needless to say, this increase in expected costs is not a welcome change to the project manager.
  • Billings
    This row summarizes the state of cash flows with respect to the owner of the facility; this row would not be included for reports to owners. The contract amount was $67,511,602, and a total of $9,276,621 or 13.741% of the contract has been billed. The amount of allowable billing is specified under the terms of the contract between an owner and an engineering, architect, or constructor. In this case, total billings have exceeded the estimated project completion proportion. The final column includes the currently projected net earnings of $966,339. This figure is calculated as the contract amount less projected costs: 67,511,602 - 66,545,263 = $966,339. Note that this profit figure does not reflect the time value of money or discounting.
  • Payables
    The Payables row summarizes the amount owed by the contractor to material suppliers, labor or sub-contractors. At the time of this report, $6,719,103 had been paid to subcontractors, material suppliers, and others. Invoices of $1,300,089 have accumulated but have not yet been paid. A retention of $391,671 has been imposed on subcontractors, and $343,653 in direct labor expenses have been occurred. The total of payables is equal to the total project expenses shown in the first row of costs.
  • Receivables
    This row summarizes the cash flow of receipts from the owner. Note that the actual receipts from the owner may differ from the amounts billed due to delayed payments or retainage on the part of the owner. The net-billed equals the gross billed less retention by the owner. In this case, gross billed is $9,276,621 (as shown in the billings row), the net billed is $8,761,673 and the retention is $514,948. Unfortunately, only $7,209,344 has been received from the owner, so the open receivable amount is a (substantial!) $2,067,277 due from the owner.
  • Cash Position
    This row summarizes the cash position of the project as if all expenses and receipts for the project were combined in a single account. The actual expenditures have been $7,062,756 (calculated as the total costs of $8,754,516 less subcontractor retentions of $391,671 and unpaid bills of $1,300,089) and $ 7,209,344 has been received from the owner. As a result, a net cash balance of $146,588 exists which can be used in an interest earning bank account or to finance deficits on other projects.
  • Each of the rows shown in Table 12-8 would be derived from different sets of financial accounts. Additional reports could be prepared on the financing cash flows for bonds or interest charges in an overdraft account.

    TABLE 12-8  An Example of a Cash Flow Status Report

    TABLE 12-8  An Example of a Cash Flow Status Report

    The overall status of the project requires synthesizing the different pieces of information summarized in Table 12-8. Each of the different accounting systems contributing to this table provides a different view of the status of the project. In this example, the budget information indicates that costs are higher than expected, which could be troubling. However, a profit is still expected for the project. A substantial amount of money is due from the owner, and this could turn out to be a problem if the owner continues to lag in payment. Finally, the positive cash position for the project is highly desirable since financing charges can be avoided.

    The job status reports illustrated in this and the previous sections provide a primary tool for project cost control. Different reports with varying amounts of detail and item reports would be prepared for different individuals involved in a project. Reports to upper management would be summaries, reports to particular staff individuals would emphasize their responsibilities (eg. purchasing, payroll, etc.), and detailed reports would be provided to the individual project managers. Coupled with scheduling reports described in Chapter 10, these reports provide a snapshot view of how a project is doing. Of course, these schedule and cost reports would have to be tempered by the actual accomplishments and problems occurring in the field. For example, if work already completed is of sub-standard quality, these reports would not reveal such a problem. Even though the reports indicated a project on time and on budget, the possibility of re-work or inadequate facility performance due to quality problems would quickly reverse that rosy situation.

     

     
     
     